Sample Status Metrics Used to Manage Project


In order to accurately judge where we were at any given time, we had to have quantitative metrics and be able to report on them. During the course of the project I developed a number of reports and graphs that we used every week. The first is a graph tracking the contractor’s systems testing progress (actual vs. baseline). The second is a chart detailing the progress of system error correction. The columns refer to the subsystems undergoing testing.